how to prepare Bar Bending Schedule (B.B.S) of Compound wall

Bar Bending Schedule (B.B.S) is list of Steel Drawing document, which include detail section of Particular Item, in this section you will get such detail as, shape of bars, diameter of bars, length of bars, lap of bars and it also include some General Thumb rules in Bar Bending Schedule but the main part is how to prepare bar bending schedule for construction site.

which data require to prepare Bar bending schedule (B.B.S)

how to calculate Unit weight of steel bars per meter formula (kg/m)

Method 1: – calculate weight of 12 mm bars

Weight (kg/m) = Volume x Density weight = (3.14/4 x d2 (12 mm = 0.012 m) x Density (7850) weight = ((3.14/4) x (0.012 x 0.012) x 7850 Weight = (0.785 x 0.000144 x 7850) = 0.89 kg/m 12 mm Dia weight for 1.00 meter = 0.89 kg/m

Method 2: calculate weight of 12 mm bars

weight = d2/162 weight = (12×12)/162 = 0.89 kg/m 12 mm Dia weight for 1.00 meter = 0.89 kg/

sr.noDia of barWeight of bar for 1 m length (kg/m)
1 8 0.39
2 10 0.62
3 12 0.89
4 16 1.58
5 20 2.47
6 25 3.86
7 28 4.84
weight of steel bar

Clear Cover as per IS 456

Footing cover as per IS 456 – 50 mm

Column cover as per IS 456 – 40 mm

Beam cover as per IS 456 – 25 mm

slab cover as per IS 456 – 25 mm

thumb rule for bar bending schedule

thumb rule for column

  1. every floor one no of lap consider in column.
  2. not more than 50% bar lapped in one junction.
  3. Minimum 12 mm diameter use in column.
  4. Hook for Ring = 10 x diameter

thumb rule for Beam

  1. Bottom bar lap should be at column junction.
  2. Top bar lap should be at center of columns.
  3. Ring Distance as per design drawing.
  4. Consider 1 no of lap at every 12.00 m

thumb rule for Slab

  1. Provide Main steel at shorter span and Distribution steel at longer span
  2. Spacing of main steel is 3D or 300 whichever is more and for Distribution steel 5D or 450 mm whichever is more
  3. Provide extra top bar as per design drawings.

B.B.S of Compound wall sample excel file

let’s start to prepare Bar bending schedule (B.B.S) of Compound wall.

compound wall plan

How to find footing Quantity?

how to prepare bar bending schedule (BBS)

Data- 10T @150 c/c both ways, footing cover 50 mm (0.050 m), 9 no’s of footing

  1. Footing size (1000 x 1000 x 250 mm)

No of bars in long site and short site same so = 2 x (L- (2 x cover))/150 +1 No of bars = 2 x (1000- (2×50))/150+1 No of bars = 2 x (900/150) +1 No of bars = 2 x 7 (no in one side) = 14 no

Length of cutting bar = (Length- (2 x cover)) + L (both side Length of cutting bar = (1000-(2 x 50)) + (2 x 150) length of cutting bar = 900+300 = 1200 mm = 1.2 m

For Double footing at Expansion joint at every 30 m

2. Footing size =(1450 x 1000 x 250 mm), Steel 10T@150 mm c/c both ways

How to prepare bar bending schedule (B.B.S)

No of bars in long site = (L- (2 x cover))/150 +1

No of bars = (1450- (2×50))/150+1 No of bars = (1300/150) +1 = 10 no

Length of cutting bar = (Length- (2 x cover)) + L (both side Length of cutting bar = (1000-(2 x 50)) + (2 x 150) length of cutting bar = 900+300 = 1200 mm = 1.2 m

No of bars in short site = (L- (2 x cover))/150 +1 No of bars = (1000- (2×50))/150+1 No of bars = (900/150) +1 = 7 no

Length of cutting bar = (Length- (2 x cover)) + L (both side Length of cutting bar = (1450-(2 x 50)) + (2 x 150) length of cutting bar = 1350+300 = 1650 mm = 1.65 m

Item noItemsNoDiaLengthwidthcutting No
of bar 
No
of bar
 
Dia
lengthx directiony direction8101216
1Footing Quantity
single footing
x-direction91011.27075.600
Y-direction91011.27075.600
Double footing
x-direction11011.2708.400
Y-direction1101.451.6510016.500
sample of B.B.S Format

How do you calculate the quantity of steel in column

Given data, Column size = 0.35 x 0.35, steel = 4-12T, Ring= 8T@125 c/c, hook = 10 Dia, height below ground level = 1.2 m, above ground level = 3.0 m, clear cover = 50 mm, Ld=300mm

Height of below ground level = 1.2-0.15 (P.C.C)-0.050 (Bottom cover) + 300 = 1.3 m

no of ring up to ground level = (1.2-0.15)/0.125 +1 = 9.4. say 10 rings

Length of ring= ((L-2 x cover) + (B-2 x cover) + 10xd (hook Length of ring = ((0.35- (2 x 0.040)) + ((0.35 – (2 x 0.040) + (10×8) Length of ring = (0.35-0.08) + (0.35-0.08) + 0.16 = 0.27 + 0.27 + 0.16= 0.7 m

Height of above ground level = 3.00 + 1 lap

No of Ring = 3000/125 +1 = 25 no of ring

Item noItemsNoDiaLengthwidthcutting No
of bar 
No
of bar 
Dia
lengthx directiondirection8101216
2Column Quantity
below ground level
Column steel 4-12T (0.35×0.35)9121.31.340046.80
Ring 8T @ 125 c/c980.70.7852.5000
above ground level9123.053.05400109.80
Ring above ground level
no of ring = 3.00/0.125+1980.70.725157.5000
Add 1 lap 50 x d9120.450.4540016.20
calculate Quantity column steel

how to find steel quantity in beam

Beam size = (0.230 x 0.375), Bottom- 4-12, Top- 3-10, Ring- 8T@125 c/c, beam length = 30 m, cover-25 mm. Lintel size= (0.230×0.115) bottom-2-10T, top= 2-8T, Ring – 8T@125 c/c

Length of beam steel = Length – (2 x cover) + (2 x L) Length of beam steel = 30-(2 x 0.025) +(2 x 0.15) Length of beam steel = 30.25 m + 2 lap (take every 12 m 1 lap)

Ring length = (0.230- 2 x 0.025) + (0.375- 2 x 0.025) +0.160 = 0.665 m. No of ring = 3.00 c/c so in to in (3.00-0.35 (column)) = 2.65 m

Lintel

Length of lintel beam = 30-(2 x 0.025) + (2 x 0.050) = 30.05 m. Ring Length = (0.230-2 x 0.025 + (0.115-2 x 0.025) +0.160 = 0.405 m

Item noItemsNoDiaLengthwidthcutting No
of bar
 
No
of bar 
Dia
lengthx directiony direction8101216
3Beam & lintel Quantity
Beam
bottom bar – 4-1211230.2400120.80
Top bar – 3-10 11030.23090.600
2 lap (50xd)2120.62002.40
top bar 2 lap2100.520200
Ring1080.6650.66522147.63000
Lintel
bottom bar – 2-1011030206000
Top bar – 2-81830260000
2 lap for bottom bar2100.520200
2 lap for top bar280.421.6000
Ring1080.4050.4052289.91000
BAR BENDING SCHEDULE

Total Quantity (footing + column + beam + lintel)

8T = (52.5+157.5+147.6+60+1.6+89.91 = 509.1 x 0.395 (8mm Dia weight) = 201.10 kg. 10T = 75.6+75.6+8.4+16.5+90.6+2+60+2 = 330.7 x 0.617 (10 mm Dia weight) =204.1 kg. 12T = 46.8+109.8+16.2+120.8+2.4 = 296 x 0.89 (12 mm Dia weight) = 263.1 kg. Total weight of steel = 201.10+204.1+263.1 = 668.4 kg

Leave a Reply

Your email address will not be published. Required fields are marked *

WhatsApp Group Join Now
Telegram Group Join Now
Instagram Group Join Now