What is barbed wire fencing?

A barbed wire fencing is a Type of Compound wall. which use to protect boundary from people or animals that can damage the property. so, it helps the reduce the property loss although its cost effective compared to brick work compound wall or panel fencing.

Types of Compound wall: –

There are many types of compound wall but these three-compound wall commonly use in large area to protect our boundary.

Brick work compound wall

barbed wire fencing

Panel fencing

what will you get in this blog?

  • How to find Quantity of barbed wire
  • How to prepare Estimate for barbed wire fencing
  • How to find Item rate and prepare Abstract sheet for barbed wire fencing
  • Barbed wire fencing Estimate excel sheet
  • How much cost barbed wire for 1.00 meter
barbed wire fencing detail estimate

Estimate for barbed wire fencing.

let’s take data for Prepare estimate barbed wire fencing – (For 30 m, spacing 3.00 m)

1. R.C.C pre-post (M-20 grade of concrete with vertical bar6 mm # 4 no, 4 mm # 7 no of ring equally spaced with 9 no of holes.) size of R.C.C Pre-post-12.50 cm x 12.50 cm x 2.3 m (Height 2. R.C.C Pre-post foundation size (take 1:3:6 concrete) – 50 cm x 50 cm x 60 cm 3. Barbed wire – 9 Horizontal wire and 2 diagonal wires (minimum weight (9.8 kg/ 100 meter 4. fitted and fix with G.I. Bending wire (minimum 16 SWG) fix with 6 mm bar 5. include excavation, formwork and whitewashing two or coat on Rost

How to find Quantity of barbed wire fencing

which item use in barbed wire fencing and its item unit.

Sr.noItemUnit
1Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.  All kinds of soil.M3
2Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering – All work up to plinth level: 1:3:6 (1 cement: 3 fine sands: 6 graded stone aggregate 40 mm nominal size)M3
3Centering and shuttering including strutting, propping etc. and removal of form for all heights:
 Foundations, footings, bases of columns, etc. for mass concreteM2
Centering and shuttering including strutting, propping etc. and removal of form for all heights:M2
4Reinforced cement concrete work in wall (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering shuttering, finishing and reinforcement :1:1.5:3 (1 cement :1.5 coarse sand (zone iii): 3 graded stone aggregate 20 mm nominal sizeCum
5Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete up to plinth level: Thermo-Mechanically Treated bars of grade Fe-500D or more.kg
6Whitewashing with lime on surface (two or more coat) to give even shade including toughly the surface to remove all dirt dust matter drops and other foreign matterM2
7G.I. Wire 9.8 kg/100 mquintal
estimate for barbed wire fencing

How do you calculate the barbed wire fencing

For calculate 30.00 m, (30/3) 10 Pre-post column

Item- 1. (Excavation for Post Up to 1.5m depth) = 10 (no) x 0.50 (Length) x 0.50 (width) x 0.6 (depth) = 1.5 M3

find Rate for Item-1 (DSR (volume-1) page no-74) = 181.85 M3

Item-2. Concrete (1:3:6) in foundation = 10 (no) x 0.50 (Length) x 0.50 (width) x 0.6 (depth) = 1.5 M3

find Rate for Item-2 (DSR (volume-1) page no-86) = 6126.25 M3

Item-3. (A) Centering in foundation – 10 (no) x 4 (side) x0.5 (width) x 0.6 (depth) = 1.2 M2

Item-3 (B) Centering for Pre-post column = 10 (no) x 4 (Side) x 0.125 x 2.3 (height) = 11.5 M2

find Rate for Item-3 (DSR (volume-1) page no-96) = 284.25 M2 & 773.70 M2

Item-4. R.C.C concrete work (1:1.5:3) = 10 (no) x 0.125 x 0.125 x 2.3 = 0.36 M3

find Rate for Item-4 (DSR (volume-1) page no-95) = 9306 M3

Item-5. Steel for column = 17.95 (Download B.B.S)

Item-6. whitewashing on Pre-post Column = (1) 10 (no) x 4 (side) x 0.125 x 2.3 = 11.5 M2 (2) Top = 10 (no) x 0.125 x 0.125 = 0.16. Total = 11.5+0.16 = 11.66 M2

find Rate for Item-6 (DSR (volume-2) page no-131) = 9306 M3

Item-7. barbed wire (9.8 kg/100 m) = 9 (horizontal wire) + 10 (diagonal wire between 3 Pole = (9 x 30) + (10 x 6.32) = (270 + 63.2) = 333.2 m X (9.8 kg/ 100 m) = 31.24 kg =0.31 Quantal.

find Rate for Item-4 (DSR (volume-2) page no-297) Code- 1029 = 5500 Quintal

Estimate for Barbed wire fencing

let’s start to Prepare Abstract sheet for barbed wire fencing

ABSTRACT
Sr.noDescriptionQtyRateUnitAmount
1Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.  All kinds of soil.1.50181.85M3272.78
2Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering – All work up to plinth level: 1:3:6 (1 cement: 3 fine sands: 6 graded stone aggregate 40 mm nominal size)1.506126.25M39189.38
3Centering and shuttering including strutting, propping etc. and removal of form for all heights:
 Foundations, footings, bases of columns, etc. for mass concrete1.20284.85M2341.82
Centering and shuttering including strutting, propping etc. and removal of form for all heights:11.50773.70M28897.55
4Reinforced cement concrete work in wall (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering shuttering, finishing and reinforcement :1:1.5:3 (1 cement :1.5 coarse sand (zone iii): 3 graded stone aggregate 20 mm nominal size0.369306.00CUM3344.34
5Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete up to plinth level: Thermo-Mechanically Treated bars of grade Fe-500D or more.17.9583.50kg1498.88
6Whitewashing with lime on surface (two or more coat) to give even shade including toughly the surface to remove all dirt dust matter drops and other foreign matter11.667.80M290.92
7G.I. Wire 9.8 kg/100 m0.315500.00Quantal1705.00
TOTAL25340.66
Estimated cost of 30 m.25340.66
Abstract sheet for barbed wire fencing

Barbed wire fencing pdf of Excel file?

Similar Posts

Leave a Reply

Your email address will not be published. Required fields are marked *

WhatsApp Group Join Now
Telegram Group Join Now
Instagram Group Join Now